Fire fighting water spray system for Transformers & inert gas fire suppression system IG-541 for Generators: Luang Prabang Hydropower Project in Laos

PROJECT INFORMATION:

Project name: Luang Prabang Hydropower Plant

Client: Andritz Hydro GmbH

Turbine type: Kaplan

Capacity: 1,460MW (7x200MW + 3x20MW)

Scope of work: Design, supply equipment & materials, supervision of installation and commissioning of:

– Fire fighting water spray system (deluge valve) for Transformers, Shunt reactors & Neutral reactors;

– Fire suppression system using inert gas IG-541 (inergen – 52% nitrogen, 40% argon, 8% carbon dioxide).

Location: Houygno village, Chomphet district, Luang Prabang province, Laos

Execution time: In progress